A RESOLUTION DETERMINING THE NECESSITY TO REPAIR AND/OR REPLACE SIDEWALKS IN THE 2026 SIDEWALK MAINTENANCE LOOKBACK PROGRAM AREA FOR THE CITY OF GAHANNA
BODY
WHEREAS, the City of Gahanna is committed to maintaining the public sidewalk network in a safe and functional condition to protect the health, safety, and welfare of the public; and
WHEREAS, the Department of Engineering has recommended the establishment of the 2026 Sidewalk Maintenance Lookback Program Area to define the properties that will be part of Gahanna's 2026 Sidewalk Maintenance Lookback Program; and
WHEREAS, the recommended 2026 Sidewalk Maintenance Lookback Program Area includes 252 parcels from properties along the following streets:
Bonnington Way - Lincolnshire Rd to Empire Dr
Caroway Blvd - Spruce Hill Dr to Summer Hill Cir
Codrington Cir - Waterbury Blvd N to Waterbury Blvd S
Depauw Ct - Waterbury Blvd to end of court
Fleetrun Ave - Landover Rd to Ronson Way
Flint Ridge Dr - Gary Lee Dr to Granville St
Harrow Dr - Lytton Way to Caroway Blvd
Howland Dr - Whitson Dr to Taylor Rd
Juniper Ln (south of Moss Oak Ave) - Moss Oak Ave to end of court
McCutcheon Rd E - Stygler Rd to end of court
Moss Oak Ave - Hines Rd to Mistletoe St
Prince of Wales Dr - Avonwick Pl to Haymarket Pl
Timothy - Bluestem to Shaker
Waterbury Blvd - Dunoon Dr W to Lytton Way
Windbourne St - Forestwood Dr to Shaker Dr
WHEREAS, upon approval of the 2026 Sidewalk Maintenance Lookback Program Area, an inspection of the sidewalk network within the program area will be conducted to identify defects and ensure that sidewalks are maintained in a good and orderly state of repair; and
WHEREAS, property owners with identified sidewalk deficiencies will be notified in writing of the deficiencies found, the estimated cost to be assessed as part of the program, and information on how to opt-out of the program; and
WHEREAS, the adoption of the 2026 Sidewalk Maintenance Lookback Program Area has been accelerated to better in...