Title: AN ORDINANCE TO AMEND ORD-0009-2023 AUTHORIZING THE MAYOR TO ENTER INTO AN AMENDED AGREEMENT WITH ELFORD, INC. FOR CONSTRUCTION MANAGER AT RISK SERVICES RELATED TO THE RENOVATION AND EXPANSION OF 825 TECH CENTER DRIVE TO INCLUDE SERVICES IN CONSTRUCTION CONTRACT 1; WAIVING SECOND READING, AND DECLARING AN EMERGENCY
Attachments: 1. DOS-RPT-03-25-24 revised, 2. ORD-0023-2024 EXHIBIT A - DOS-ATT - A133 Exhibit A - GMP1 - Draft, 3. ORD-0023-2024 EXHIBIT B - DOS-ATT - Exhibit 1, 4. 825 Tech Center - GMP1 - COTW - March 25 2024, 5. ORD-0023-2024 SIGNED - Amended Agreement with Elford Inc for CMAR Services Related to Renovation and Expansion of 825 Tech Center Drive - Construction Contract 1
Related files: ORD-0005-2024, ORD-0009-2023, ORD-0040-2024
TITLE
AN ORDINANCE TO AMEND ORD-0009-2023 AUTHORIZING THE MAYOR TO ENTER INTO AN AMENDED AGREEMENT WITH ELFORD, INC. FOR CONSTRUCTION MANAGER AT RISK SERVICES RELATED TO THE RENOVATION AND EXPANSION OF 825 TECH CENTER DRIVE TO INCLUDE SERVICES IN CONSTRUCTION CONTRACT 1; WAIVING SECOND READING, AND DECLARING AN EMERGENCY
BODY

WHEREAS, on February 20, 2023, City Council adopted ORD-0009-2023 to authorize the Mayor to enter into an agreement with Elford, Inc. for Construction Manager At Risk services for the 825 Tech Center Drive project, a project which will serve the residents of Gahanna for decades to come as the location and future home of City Hall, Police Headquarters, and the Senior Center; and

WHEREAS, the City has proceeded judiciously with both the design and the financing aspects of the 825 Tech Center Drive project; and

WHEREAS, bids to construct the project have been released for Construction Contract #1 (Guaranteed Maximum Price, or "GMP" 1), consisting of 16 disciplines as follows: general requirements, demolition, concrete, masonry, structural steel, metal framing, miscellaneous metals, rainscreen, roofing, glass and glazing, firing range equipment, elevators, electrical equipment, generators, and earth and utility work; and

WHEREAS, a total of 50 bids were received and reviewed by the City, Elford, and MSA Architects to select the subcontractors who will work to construct this portion of the project; and

WHEREAS, the total cost for GMP 1 is $20,327,613, representing 29 percent of the overall projected cost for the project and $367,997 under the projected budget established in January 2024; and

WHEREAS, approximately 14.36 percent of the total contract awards for GMP 1 have been awarded to diverse contractors and 69 percent are union-based employers; and

WHEREAS, the Administration recommends passage of the Ordinance by waiving second reading and declaring an emergency as necessary for the preservation of public peace, safety, health, and we...

Click here for full text