Senior Director of Operations Kevin Schultz reported on the 825 Tech Center
Drive project and noted that he had not provided an update since August 11,
2025. He apologized for the delay and explained that other events over the
past few months in the Council Chambers contributed to the delay. He stated
that the project continued to progress steadily and that his presentation would
cover construction activities from September, October, and part of November
2025. Director Schultz said that anyone who drove by the building saw the
ongoing transformation of the exterior. He showed a photo of the building from
August 19, 2025, and a comparison photo from November 18, 2025, just
before Thanksgiving. He highlighted the installation of all three solar arrays,
noting that two arrays sat on the Police Department side of the site and one
sat behind the building for city fleet vehicles. He reported that the city installed
all passive security measures, including the primary wall at the site entrance
and the seat walls incorporated throughout the landscaping. He added that
contractors completed the asphalt for the entire parking area the previous
week. He said they installed the parking lot lighting and most landscaping
lighting, with some ground lighting still pending. He also stated that paving on
the multi-use trail occurred late the previous week and that the landscaping
throughout the site was complete except for the beds closest to the building.
He provided an additional photo to show that landscaping near the building still
needed installation and that crews continued work on the stone columns. He
pointed out the security fence along the Police Department perimeter. He
described how the site was taking on the “park-like” character shown in
previous renderings, including defined entryways, awnings, and the
combination of softscape and pavers both in front of the building and behind it.
Director Schultz then discussed interior progress. He showed photos of the
main lobby and the planning lobby, where residents seeking specialized
zoning or building assistance would go. He noted that the terrazzo flooring
was finished in large portions of the public first-floor spaces and described
the open character created by the connection between the first and second
floors. He indicated the location of the Council Chambers and the customer
service windows, which residents would see when they entered and turned
left. Director Schultz stated that the third floor was in the “punch” stage,
meaning contractors and Elford identified items that required correction. He
explained that after Elford completed its punch work, trades corrected the
issues, and then the owner and architect team completed a second punch to
identify any additional items. He said the third floor was nearly complete aside
from punch-list items and a few flooring issues that would be addressed in
the coming weeks. He reported that crews were installing all exterior doors
and that work continued on the police locker room, which was taking shape
and nearing completion. He noted that technology installations were
underway, including networks, radio systems, and 911 systems. He added
that furniture installation would begin in early January on the third floor and
then move downward to the second and first floors in the following weeks.
Director Schultz stated that the project was approximately 88 percent
complete. He concluded by showing restroom photos and explained that