200 South Hamilton Road  
Gahanna, Ohio 43230  
City of Gahanna  
Meeting Minutes  
Committee of the Whole  
Trenton I. Weaver, Chair  
Merisa K. Bowers  
Jamille Jones  
Nancy R. McGregor  
Kaylee Padova  
Stephen A. Renner  
Michael Schnetzer  
Jeremy A. VanMeter, Clerk of Council  
Monday, July 21, 2025  
City Hall, Council Chambers  
Immediately following regular City Council at 7:00 PM on July 21, 2025  
CALL TO ORDER:  
A.  
B.  
Gahanna City Council met for Committee of the Whole on Monday, July 21,  
2025, in Council Chambers. Vice President of Council Trenton I. Weaver,  
Chair, called the meeting to order at 7:21 p.m. The agenda was published on  
July 18, 2025. President Bowers was absent from the meeting. All other  
members were present. There were no additions or corrections to the agenda.  
ITEMS FROM THE DEPARTMENT OF ENGINEERING:  
AN ORDINANCE TO LEVY SPECIAL ASSESSMENTS FOR CERTAIN  
REAL ESTATE WITHIN THE 2022 SIDEWALK MAINTENANCE  
PROGRAM, TO APPROVE COSTS AND QUANTITIES, AND TO  
DECLARE AN EMERGENCY  
Director of Engineering Tom Komlanc noted the department had four items  
before the Council that evening. He explained that the first two items related to  
the sidewalk maintenance and Americans with Disabilities Act (ADA)  
transition program, specifically the 2022 and 2024 programs, following the  
conclusion of construction activities, and that they were before the Council for  
the assessment and public hearing. He reviewed the background, noting that  
the 2021 program was completed in 2023, produced lessons learned, and  
prompted an update to the code. He said the 2022 program, which was in the  
works in 2023, went through construction, and that they aimed to align the  
program years with the actual years of construction, so the 2024 program  
occurred in 2024. Komlanc reported that they tallied quantities, calculated the  
final field-measured quantities, and provided notice to the residents within the  
program area. He said the public hearing for both programs was slated for  
August 4, 2025.  
Councilmember Jones asked for clarification on the cost summary,  
specifically the owner-attributed defect cost versus the total, and noted that  
the resident was only responsible for 50% of the defect costs. Komlanc  
introduced Paige Wright, Senior Transportation and Mobility Engineer, who  
administered the program. Wright explained that the total cost included  
defects attributed to the resident as well as those attributed to the city, giving  
examples such as panels associated with curb ramps or panels with issues  
around water valves that the city identified and replaced at full city cost; the  
resident would pay only the owner-attributed portion, excluding any costs the  
city identified as its own. Jones confirmed that the resident paid only 50% of  
that owner-attributed cost, and Wright agreed.  
Vice President Weaver said he understood that these items wrapped up the  
2022 and 2024 programs and that the 2023 program was completed.  
Komlanc clarified that because of the pause for the code updates, they  
moved into 2024 by the time they engaged the 2023 program. Weaver  
confirmed that no additional items would come forward for the 2023 program,  
and Komlanc concurred.  
Recommendation: Introduction/First Reading with Public Hearing on Regular  
Agenda on 8/4/2025; Second Reading/Adoption on Regular Agenda on  
8/18/2025.  
AN ORDINANCE TO LEVY SPECIAL ASSESSMENTS FOR CERTAIN  
REAL  
ESTATE  
WITHIN  
THE  
2024 SIDEWALK  
MAINTENANCE  
PROGRAM, TO APPROVE COSTS AND QUANTITIES, AND TO  
DECLARE AN EMERGENCY  
Recommendation: Introduction/First Reading with Public Hearing on Regular  
Agenda on 8/4/2025; Second Reading/Adoption on Regular Agenda on  
8/18/2025.  
A MOTION AUTHORIZING THE CITY OF GAHANNA BIDDING FOR THE  
2025 STREET REBUILD AND SIDEWALK MAINTENANCE PROGRAM  
WITH WATERLINE REPLACEMENT (ST-1116)  
Director of Engineering Tom Komlanc presented the next two items, which  
first involved a request for permission to bid the street rebuild and waterline  
project for Laura, Heil, and Rocky Fork Drive North. He said the plans were  
finalized and they sought permission to proceed with contracting.  
Councilmember Padova asked whether the Rocky Fork project would include  
sidewalks on both sides, and Komlanc confirmed it would. She then asked  
about Laura and Heil, where existing sidewalks appeared only on one side,  
and whether the project would remove and replace the existing sidewalks or  
add new ones on the opposite side. Komlanc explained that the project would  
remove and replace some existing sidewalk facilities to achieve ADA  
compliance; in areas without sidewalks, staff held a public meeting, and  
residents had expressed a desire not to install new sidewalks. No valid  
petition for assessment came forward, so they would not add sidewalks in  
those areas, but they would make improvements where sidewalks already  
existed. Padova confirmed that the team already met with the residents and  
communicated those decisions for both Laura and Heil and Rocky Fork, and  
Komlanc agreed. Padova asked whether the project appeared in the 2025  
budget but would occur in 2026; Komlanc replied that it was part of the 2025  
budget, that the waterline work would occur over the winter, and that the  
rebuild would take place in the spring of the following year.  
Councilmember McGregor raised a question about Rocky Fork Drive North,  
on the north side, regarding some driveways and how the sidewalks would  
work there. Komlanc said they performed engineering design to resolve the  
profile grades and that the design worked. McGregor commended the  
experts.  
Recommendation: Adoption on Consent Agenda on 8/4/2025.  
A MOTION AUTHORIZING THE CITY OF GAHANNA BIDDING FOR THE  
TAYLOR ROAD WATER MAIN REPLACEMENT PROJECT  
Director of Engineering Tom Komlanc requested permission to bid the Taylor  
Road waterline replacement from Morrison Road to Helmbright. He said the  
project would upsize the existing 12-inch line to a 16-inch line to  
accommodate anticipated regional growth and the growth the city was  
experiencing, and to provide resiliency to the potable water distribution  
system network.  
Recommendation: Adoption on Consent Agenda on 8/4/2025.  
C.  
ITEMS FROM THE DEPARTMENT OF ECONOMIC DEVELOPMENT:  
AN ORDINANCE TO REAUTHORIZE AND AMEND THE CREEKSIDE  
OUTDOOR REFRESHMENT AREA (CORA) IN ACCORDANCE WITH  
OHIO REVISED CODE 4301.82  
Director of Economic Development Jeff Gottke presented four slides  
regarding the reauthorization of the Creekside Outdoor Refreshment Area  
(CORA), noting that the statute required the Council to review and reauthorize  
CORA after five years of initial implementation, which would occur in  
mid-August. He reviewed the fundamentals of a Designated Outdoor  
Refreshment Area (DORA), referred to locally as CORA, as outlined in  
Revised Code 4301.82, including the requirements that the area remain no  
more than 320 contiguous acres, display permanent boundary signs, allow  
businesses and liquor license holders to opt in or out, post the rules clearly,  
and use designated non-glass containers (plastic cups in warmer months  
and insulated cups for hot liquids in colder months). He explained that the  
program required an approved health and safety plan, which designated at  
least one officer for the area with the option to add more, and an approved  
sanitation plan from Parks and Recreation and the Service Department that  
provided receptacles at each CORA establishment and throughout the area,  
maintained by the city. He added that the CORA committee met annually,  
which was above and beyond the legal requirement, to review the prior year’s  
performance, and that participation had to align with the master land use plan  
and include at least four participants holding qualifying liquor licenses; servers  
also had to receive special training.  
Director Gottke reported successes from 2023 and 2024, stating that the  
annual review group, which included city staff from development, safety,  
sanitation services, and parks, along with business owners and Visit  
Gahanna stakeholders, met to evaluate the program. They sold almost  
14,000 CORA cups over that period, and, using a conservative $6 per  
beverage estimate, that equated to approximately $84,000 in direct revenue to  
participating establishments, with additional induced economic benefit as  
patrons lingered, enjoyed green spaces, shopped, and dined. He said Chief  
Spence reported zero CORA-related incidents that year involving businesses,  
underage consumers, or the general public. He also noted that sanitation staff  
observed no increase in service demand or additional trash collection due to  
CORA in the district, indicating the program operated as intended. He then  
described two changes that participating businesses requested, which the  
committee discussed and agreed to pending Council approval. He explained  
that the Council would act in a single piece of legislation to both reauthorize  
CORA for five more years and implement the two changes. The first change  
would establish uniform hours of 11:00 a.m. to 11:00 p.m. daily, effectively  
expanding the existing Monday through Wednesday window from 3:00 p.m. to  
11:00 p.m. by starting earlier. The second change would expand the eastern  
boundary of the CORA by one block to include the west side of Short Street,  
adjusting the area eastward and squaring off its southern edge where Short  
Street ends and jogs toward High Street so that additional businesses could  
participate. He outlined the next steps in the process: the Council would hold  
a public hearing on August 4, 2025, followed by a second reading and vote on  
August 18, 2025. He then invited questions.  
Councilmember Renner asked whether all the businesses in the CORA area  
supported the program or if some opted out, and whether any displayed “no  
CORA” stickers. Director Gottke said he did not know how many businesses  
had such stickers. Mayor Jadwin said she was not aware of any business  
that requested or displayed a “no CORA” sticker since the program began in  
2020. Renner added that he had not seen any but did not clearly remember.  
Renner then asked whether the proposed expanded area for CORA included  
spaces that might develop in the future, specifically referring to CIC-owned  
property. Gottke replied that the property on Granville Street or Mill Street  
already lay within the existing CORA and that the proposed expansion would  
include additional properties on High Street.  
Councilmember McGregor confirmed that no businesses currently operated  
in the expanded area; Gottke explained that businesses in that vicinity  
requested the expansion so the Council could include them. Mayor Jadwin  
cited the Fable Collection at the corner of High and Carpenter as an example,  
noting the business regularly scheduled a Creekside boutique hop that  
brought vendors to North Street, and that the current boundary prevented  
patrons from carrying beverages beyond that point or moving northward into  
her business. She added that Sergeant Coffee, which moved into the former  
Fox and Fox location on the other side of the street, also factored into the  
adjustment, and that the expansion would extend the boundary from the  
sidewalk in front of the business to the sidewalk behind the buildings on the  
east side of High Street. McGregor asked whether the expansion moved  
CORA closer to or within any prohibited area around schools. Gottke  
responded that the revised code did not require any prohibited area around  
schools. Mayor Jadwin said that, when they first created the DORA, they  
chose to include such a limitation as a precaution, but she did not believe any  
prohibition or restriction in the code currently imposed that limitation and  
noted that the issue had not arisen over the past five years. McGregor  
clarified that while no prohibition existed on selling alcohol within the CORA  
boundary, certain liquor license objections could prohibit sales within 500 feet  
of a school; Gottke explained that CORA’s boundary did not affect that  
restriction, and if such an objection existed, they would carve that area out of  
CORA, but no such objection applied at that time.  
Vice President Weaver asked about signage marking the end of the CORA  
boundary and whether the signs would move with the proposed expansion  
toward Carpenter. Mayor Jadwin said they would have to adjust the signage.  
She then added that, in support of sustainability initiatives, the CORA used  
compostable cups and that the city received a $35,000 grant from SWACO  
(Solid Waste Authority of Central Ohio) to install recycling containers  
specifically for CORA cups throughout the district, which did not increase  
sanitation workload but reduced actual trash by diverting recyclables.  
Councilmember Padova inquired about the jog in the boundary around The  
Sanctuary and asked whether Lola and Giuseppe’s was asked to participate.  
Mayor Jadwin said they declined. Padova suggested considering a future  
expansion to include the Collective Home Supply for similar reasons as the  
Fable Collection. Gottke noted they did not have to wait five years to expand  
and could bring that back at another time, explaining that the timing simply  
aligned for the current proposal. Mayor Jadwin reiterated that the purpose of  
having a DORA involved creating a walkable area where patrons could move  
from establishment to establishment within a defined boundary and said they  
discussed further eastward expansion but did not believe the conditions yet  
warranted it. As new businesses appeared along Granville Street and  
enhanced walkability, they would adjust the boundary as appropriate. Padova  
asked about the process for new restaurants entering the defined area, and  
Gottke said the city would reach out to those businesses.  
Vice President Weaver thanked Gottke for bringing the item forward,  
expressed support for the standardized hours to reduce confusion, and  
appreciated Padova’s question and Mayor Jadwin’s explanation. He observed  
that the zoning map showed the Creekside mixed-use zoning extending down  
Granville Street, making future expansion potentially appropriate, but said he  
felt comfortable with the current proposal. With no further discussion, he  
requested that, because the item included a public hearing, it remain on the  
regular agenda.  
Recommendation: Introduction/First Reading with Public Hearing on Regular  
Agenda on 8/4/2025; Second Reading/Adoption on Regular Agenda on  
8/18/2025.  
Returning for Further Discussion (Postponed 7.7.2025):  
AN ORDINANCE AUTHORIZING THE MAYOR TO ENTER INTO A  
COMMUNITY REINVESTMENT AREA AGREEMENT WITH VELOCIS  
GAHANNA JV, LP TO FACILITATE THE CONSTRUCTION OF AN  
INDUSTRIAL  
BUILDING  
ON  
PARCELS  
027-000110-00 AND  
025-13634-00 ON TECH CENTER DRIVE, PART OF COMMUNITY  
REINVESTMENT AREA #3; AND DECLARING AN EMERGENCY  
Director of Economic Development Jeff Gottke began by saying he thought it  
would be helpful to summarize the questions and issues the Council raised to  
provide clarity for its decision. He noted that he provided a printed memo,  
prior to the meeting, and that he planned to use a few slides, mostly graphics  
from the memo, to crystallize those issues. He said company representatives  
were present to speak in more depth afterward and that Mayor Jadwin  
planned to offer comments. He identified four major questions the Council  
asked during the process: whether the project proved financially worth it for  
the city; how it compared to other abatement projects in the city; how the city  
knew who it was doing business with; and whether the community needed  
this type of building in Gahanna.  
On the first question, financial worth, Gottke explained that the Council  
historically applied a “but for” standard, i.e., the project would not occur but for  
the abatement, and that the abatement in this case made rent affordable for  
potential tenants. He displayed gross rent with and without the abatement and  
compared those figures to the regional average to demonstrate that the  
affordability measure aligned with the market. He then addressed return on  
investment, presenting pre-abatement payments from the property  
(approximately $11,000 to schools, about $406 to the city, and $0 to a TIF)  
versus during the abatement (school collections rising to $102,000 and city  
collections, including income tax and the TIF’s 20% remaining payment,  
increasing to $52,000) and post-abatement (school collections jumping to  
$226,000 and city receipts increasing to $213,000 via TIF and income tax). He  
added a previously omitted piece of data: construction activity would generate  
roughly $153,000 in income tax collections over the next year, which he  
characterized as additional upside for the city. He said he calculated the  
percentage increases from the current annual amounts to year 13 and that  
those increases represented a strong return on investment. On job creation,  
Gottke referenced an appendix comparing six other speculative projects in the  
city and reviewed their 2024 performance relative to their pledges. He  
reported that those projects delivered 17 more jobs than pledged, $2.4 million  
more in payroll, and $17,000 more in salary than they had promised, providing  
data that speculative developments could perform and contribute economic  
value.  
Addressing the second question, how this project compared to other  
abatement projects, Gottke first reviewed the nine abatements in CRA Area 3.  
He said the proposed project ranked second in total investment, fourth in job  
creation, and fifth in payroll (noting it was the only one with guaranteed  
payroll); its abatement term tied for fourth and its abatement percentage tied  
for fifth. He then compared it to the other five speculative developments in the  
city, stating that it ranked third in total investment, fifth in job creation, second  
in total payroll (with the caveat that none of the others guaranteed payroll),  
second in salary, and second in building and parcel size. He noted that the  
abatement term and percentage fell in the middle of the range, which  
spanned from seven years at 75% to 15 years at 100%, and concluded that  
the project offered above-average returns with an average term and rate.  
On the third question, how the city knew who it was doing business with,  
Gottke deferred detailed discussion to the company representatives,  
acknowledging they knew their own background best, but he outlined the  
city’s vetting process. He said the incentive application included questions  
about delinquent taxes, and staff, when appropriate, consulted other  
departments regarding property maintenance violations or code deficiencies  
to verify compliance. He emphasized the value of Jobs Ohio’s involvement,  
explaining that the organization deployed hundreds of millions of its own  
dollars in grants and loans for economic development, only supported net  
new projects in the state, and limited incentives to eleven economic-based  
industry sectors that brought external dollars into the community. He said  
Jobs Ohio conducted its own rigorous vetting because it invested its own  
funds. He noted that the packet included the Jobs Ohio intake/project  
introductory application and the Ohio Site Improvement Program application  
for speculative site development, highlighting sections addressing company  
history and reputation. He added that since 2011, Jobs Ohio completed 2,800  
projects with 500 different companies and invested hundreds of millions of  
dollars of its own capital.  
On the fourth question, whether the city needed this type of building, Gottke  
described the proposed facility as a flexible industrial warehouse with an  
office component designed to accommodate light manufacturing or  
warehousing with associated office space. He referenced a spreadsheet that  
Nate Green had shown at the prior meeting and said they received site  
requests from Jobs Ohio roughly weekly or every other week. He explained  
that since 2024 the city lacked appropriate sites for those requests, so they  
could not submit several prospective projects; he presented those unmet  
requests, detailing square footage, jobs, investment, intended use, and  
industry. He distinguished existing industries (highlighted in blue) from ones  
not yet present (in white), noting that existing industries tended to attract  
similar firms through clustering, while also aiming for a diversified economy.  
He said those peer comparisons also helped verify the company’s claim of  
creating 37 jobs. Gottke then discussed the benefits of available space,  
analogizing the situation to a homeowner choosing to rent versus buy. He  
said businesses leased space for speed to market, that emerging companies  
needed immediate space, that midsize growing companies required  
transitional facilities, and that some firms operated as lease-only entities by  
design. He cited seven local businesses that succeeded after starting or  
expanding in similar space, noting they might have looked outside Gahanna  
had the city lacked available options. He presented June 2025 data from One  
Columbus, the regional economic development partner, showing available  
space by size and location. He said the 100,000 to 199,000 square foot  
category had the fewest buildings in the region, indicating demand, and that  
sales data supported that demand. He reported that 77% of all buildings  
leased in the second quarter of the year fell between 50,000 and 300,000  
square feet, likely concentrating in the 100,000 to 200,000 range, with those  
buildings varying in condition and amenities. He said the proposed building  
would provide Class A space in a prime location for transportation, travel, and  
quality of life in the Columbus region, making it very attractive.  
Lastly, Director Gottke cited two recent inquiries that underscored demand:  
one Gahanna-based business seeking to expand required 15,000 to 20,000  
square feet, and a business that had left the area wanted to return and sought  
50,000 to 60,000 square feet that the proposed building could fulfill or partially  
fulfill. He concluded by saying he hoped the summary helped bring the  
discussions from prior meetings together, then turned the presentation over  
to the company representatives to address the four questions in greater depth  
and offered to take any questions.  
Questions from Council to Director Gottke  
Councilmember Padova thanked Director Gottke for the information and  
asked about the timeframe for the five speculative projects used for  
comparison on page four of the provided packet. She inquired whether those  
projects occurred in the last five or ten years. Gottke said the exhibit included  
the lengths of the abatements, noting one of them was set to expire in 2025  
and others extended out to 2037 if the current project were approved, and  
acknowledged the comparisons spanned a variety of timeframes. Padova  
summarized that the five projects being compared likely occurred over  
roughly the last ten years, and Gottke agreed.  
Councilmember Jones referred to page five of the packet, which outlined the  
economic development department’s typical vetting steps, and asked about  
the process for this particular applicant, whom she believed to be new to the  
area and the state. She asked specifically about consulting with local  
communities where the applicant had other abatements. Gottke confirmed  
the applicant was new to Ohio. He explained that economic development  
staff, just as companies inquire about doing business in Gahanna, reach out  
to other communities when aware of a project to ask about their experience  
with a developer, and they verify that information through auditor websites and  
Tax Incentive Review Council (TIRC) reporting data, acknowledging that  
some county auditors provide better systems than others. Jones noted the  
department had not been able to do that outreach within Ohio for this  
applicant.  
Vice President Weaver followed up by asking whether the department  
reached out to communities outside Ohio since there was no prior activity in  
Ohio. Gottke responded that each state had different systems and that they  
typically did not call around the country for that sort of inquiry, and he pointed  
to the involvement and support of Jobs Ohio as a significant reputability  
indicator. Weaver then asked whether the city received a completed Jobs  
Ohio application and whether Jobs Ohio provided a report back. Gottke said  
Jobs Ohio did not share their application information and that all of their  
reporting remained aggregated.  
Councilmember Jones asked if the application was related to a grant through  
Jobs Ohio. Gottke replied that the program combined multiple elements and  
that he was not certain of the exact nature of the award. Jones suggested  
they could address that question with the company representatives later.  
Discussion with Company Representatives  
Jonathan Postweiler thanked Jeff Gottke and the Council for the opportunity to  
address questions or concerns regarding the proposed ordinance on behalf  
of Velocis and KBC Advisors. He expressed his disappointment with how the  
July 7, 2025, City Council meeting transpired, saying that although he  
appreciated the diligence shown by Councilmembers, he felt troubled by the  
lack of transparency in the events leading up to that meeting and by the  
prolonged delays in the approval process. He addressed Mr. Clawson’s  
earlier comments, noting that the site sat idle for decades, generated no  
additional tax revenue, and failed to achieve its highest and best use. He said  
the City of Gahanna established a Community Reinvestment Area that  
included the site to encourage investment and job creation, a policy  
subsequent councils upheld, acknowledging the role abatements played in  
economic growth. He criticized the current process for lacking clear  
standards, ebbing with political tides, and remaining opaque and arbitrary,  
which he said created the appearance of an uneven and subjective approach  
to evaluating projects and risked diminishing the time, capital, and  
professional commitment his team made and intended to continue making.  
He compared the proposed abatement to the February 2022 approval of a  
15-year, 100% tax abatement for Scannell Properties’ 292,000-square-foot  
speculative industrial development at 1800 Deffenbaugh Court, noting that  
that project received emergency clause passage and waived second reading  
with no job creation guarantees, while their proposed project, despite being  
less than half the size, offered a shorter 12-year term, a lower 80%  
abatement, and significantly greater economic value including more than a  
half million in additional payroll and developer guarantees around payroll tax.  
He reaffirmed his team’s commitment to working collaboratively with the city  
to deliver a high-quality project that provided long-term benefits.  
Mr. Postweiler then responded to Councilmember Jones’s question about the  
Jobs Ohio approval process. He summarized that they obtained full internal  
approvals from Jobs Ohio, and that a draft grant agreement had arrived for  
review. He explained that they submitted organizational charts,  
documentation confirming good standing of relevant entities, certificates to do  
business in Ohio, and banking information as part of the grant application.  
Jobs Ohio accepted those materials without objection, completed its vetting,  
approved the project for a grant amount, and the team would execute the  
grant agreement upon receipt. Postweiler read a statement to clarify three key  
points about the proposed project. First, he said the city would incur no loss if  
the abatement received approval because the project would not proceed  
without it; he explained that approval would allow the city to receive its share  
of taxes based on increased underlying land value plus 20% of property taxes  
on the new improvements, whereas denial would leave the site undeveloped  
and continue generating the current $406 per year. He warned that denying  
the abatement would signal to future investors that Gahanna did not prioritize  
economic development or provide timely, consistent application review.  
Second, he said the city would receive guaranteed payroll tax revenue  
because the owner agreed to a binding guarantee of a minimum level of  
payroll tax generation and would compensate the city annually for any  
shortfall, with failure to pay constituting a breach and risking loss of the  
abatement, thereby mitigating the city’s risk while preserving upside if job  
creation exceeded expectations. He contrasted that with the alternative of  
zero jobs and zero payroll tax if the ordinance failed. Third, he argued that  
evaluating the project solely through the 12-year abatement window proved  
short-sighted because the facility would operate for decades beyond that  
term, generating sustained economic and public value, and once the  
abatement ended, full tax revenues would flow to the city, school district, and  
other public entities.  
Councilmember Jones asked Postweiler to elaborate on the relationship  
between KBC and Velocis, including their joint history, locations of past  
projects, and end users. Postweiler said he led the Midwest development  
team for KBC and the Velocis team, that the partnership between KBC and  
Velocis encompassed over $1 billion in industrial warehouse projects across  
15 developments totaling more than 8.5 million square feet, and that their  
investor base included large pension funds, endowments, insurance  
companies, family offices, and private investors. He said Velocis,  
headquartered in Dallas, operated as a private equity real estate fund  
manager founded in 2010, raised over $1.6 billion in equity, acquired more  
than $3.3 billion in real estate assets across over 220 investments, and  
launched eight actively managed funds spanning 70 property types. He added  
that the KBC-Velocis partnership’s 15 projects spanned the Southwest in  
Arizona and Texas, the Chicago area, and were now expanding into Ohio. He  
said 14 of those 15 developments proceeded without issue, noting one  
project faced ongoing litigation, and affirmed the partnership’s commitment to  
transparency and ethical business, characterizing the litigation as an  
anomaly. Councilmember Jones asked why the team chose Ohio. Postweiler  
responded that two factors drove the decision. He introduced listing brokers  
Beau Taggart and Joe Kimener, noting they had deep industrial brokerage  
experience and understood the local market demand. Strategically, he said  
Ohio provided access and connectivity to most of the eastern United States  
within one day’s drive, favorable fiscal policies, tenant demand, interstate  
connectivity, access to labor, and strong market dynamics in Columbus. He  
added that submarket dynamics on the east side of town and Gahanna’s  
community reputation, including being the best-ranked ZIP code two years in  
a row, strong labor market, and interstate access, further influenced their  
decision. He concluded that a site owned by VRG became available to  
acquire, prompting them to put it under contract and begin the process. Jones  
then raised the issue of the litigation in Texas, asking about the prior  
relationship with that community, the origin of the dispute, and how the  
situation escalated to litigation rather than resolution through dialogue.  
Postweiler prefaced his response by stating the matter remained active  
litigation and that he would speak within appropriate bounds. He said the  
litigation involved the Texas development team in conjunction with Velocis,  
and that he, being based in the Midwest, did not handle daily operations but  
remained aware of the situation. He explained that the site in question fell  
under a master development plan and extraterritorial development agreement.  
Velocis acquired a small portion, followed the same procedures previous  
developers used to permit the site, received approvals from a privately  
appointed design review committee and the county board, and notified the  
City of Bee Cave of construction commencement. He said the city provided  
no pushback at that time and only filed a lawsuit after residents began to  
complain. He reported that Velocis contested the city’s allegations of zoning  
violations and filed a counterclaim arguing that the lawsuit violated Chapter  
245 of the Texas Local Government Code, due process and property rights  
under Texas and U.S. Constitutions, and the Texas Open Meetings Act,  
asserting that the decision to sue occurred without proper public notice. He  
said, to his understanding, Velocis received the suit without prior notice, no  
public meetings occurred to discuss the litigation, and that circumstance  
prevented meaningful engagement with the community about next steps. He  
added two caveats: first, the lawsuit aimed to stop construction despite the  
buildings nearing completion, noting a temporary injunction had lifted at the  
first hearing and that the trial set for February concerned stopping  
construction on buildings already complete, making the issue largely moot;  
second, he said their submitted statement reflected that the city and Velocis  
each strongly disputed the other’s positions, with Velocis alleging neglect,  
crime, improper procedures, and other deficiencies on the city’s part.  
Councilmember Padova corrected the record, stating that the Scannell  
Properties 2022 abatement ordinance had passed with a waiver but that the  
emergency clause had failed; she and Councilwoman Bowers had voted no  
on the emergency. Jonathan Postweiler acknowledged the correction.  
Councilmember Schnetzer said the notification of the ongoing litigation in  
Texas had slowed the process and asked City Attorney Tamilarasan to  
summarize her assessment of the public filings. Tamilarasan reported that  
she had conducted as deep a review as possible of the public records  
involving the City of Bee Cave, Velocis, and KBC Investment Group. She said  
she would not judge the merits of the underlying case, but her concern arose  
from the parties’ actions during litigation and the complexity of the business  
structure. She explained that multiple motions to compel discovery had  
involved Velocis and KBC and that she lacked access to the detailed  
information submitted to Jobs Ohio, such as subsidiary structures,  
organizational charts, and bank records, needed to evaluate enforceability.  
She warned that even a sound contract could fail if the contracting entity  
lacked solidity, particularly given the multiple layers of subsidiary entities,  
which created uncertainty about whether the city could ultimately collect or  
enforce obligations. Schnetzer asked for her opinion on the risks in the  
proposed agreement, and Tamilarasan reiterated that her concern centered  
on ensuring the city contracted with the proper, enforceable entities; given the  
limited information she had, she remained uneasy. Schnetzer then asked  
whether the city attorney’s office and the economic development office could  
work with the applicants to resolve those concerns. Mr. Postweiler responded  
with two points. First, he reminded the Council and public that being named in  
a lawsuit did not constitute an admission of guilt or evidence of wrongdoing,  
citing prior unfounded allegations against the city as illustrative of the danger  
of lending undue credibility to unproven claims. Second, he explained the  
organizational structure of the ownership and management entities, stating  
that Velocis Gahanna JV, LP would serve as the single-purpose ownership  
entity with Velocis Gahanna JV GP LLC as the managing entity, a structure  
that provided signing authority and accommodated multiple investment  
partners without requiring every investor to execute each document. He  
described the use of single-purpose entities as standard in commercial real  
estate, noting that their lender required such a structure and that banks  
performed OFAC (Office of Foreign Assets Control) checks during loan  
origination. He asserted the structure did not obscure ownership, pointed to  
similarly structured respected firms in the community, and reiterated that  
Velocis Gahanna JV, LP would not engage in any “drop and swap” practice.  
Director Gottke noted that the city attorney had previously requested an  
organizational chart and that they could provide one to help satisfy her  
concerns. Postweiler confirmed that if an organizational chart would make the  
Council comfortable approving the ordinance, they would provide it. Gottke  
added that the Council retained ultimate control over the abatement and could  
cancel it upon non-performance, restoring tax collections. Aaron Underhill,  
legal counsel for the applicant, said the Tax Incentive Review Council’s  
annual review served as a first fail-safe, and that cancellation of the incentive  
returned 100% of the taxes to their normal flow. He also noted that the  
project’s $19 million building asset gave the city a tangible entity to pursue in  
the event of a damage claim, and that the single-purpose entity would have to  
own that asset to receive the incentive during the term. Councilmember  
Schnetzer indicated a desire to move past the city attorney’s concerns and  
suggested follow-up work among the parties. Vice President Weaver clarified  
that the Tax Incentive Review Council made recommendations but did not  
hold decision-making authority. Postweiler emphasized that the proposed  
CRA included payroll tax guarantees, that failure to meet those guarantees  
would constitute a breach allowing the city to terminate the agreement, and  
that the owner would have to make annual payments to receive the benefit.  
Weaver asked who would bear responsibility if the income tax amount failed  
to materialize; Postweiler replied that Velocis Gahanna JV, LP would incur  
that obligation, and if it did not fulfill the guarantee the city would contact him  
or Paul Smith, who held signing authority for the managing entity.  
Councilmember Renner shifted topics and asked whether the speculative  
building now had identified prospective tenants, noting that earlier testimony  
had indicated no one was lined up. Gottke clarified that he had provided  
expressions of interest from companies. Postweiler added that they had  
received a full-building lease proposal the previous week from an undisclosed  
group targeting occupancy a few weeks before the projected construction  
completion; he warned that further delays in approving the abatement would  
push construction out, jeopardize that prospective tenant, and impair their  
ability to provide a reliable delivery date. Renner then asked whether they  
updated information regarding renewable energy, water use, building  
performance, or perimeter improvements. Postweiler responded that the  
delays since the last Committee of the Whole meeting imposed significant  
cost increases, especially with upcoming winter conditions affecting site work  
and foundations, eroding any remaining margin. He said they were not  
pursuing additional base-building improvements at that time, though they  
would consider retrofitting such features after delivery if tenants required  
them. Renner noted the project sought an 80% abatement; Postweiler  
reiterated that the abatement reflected demonstrated financial need based on  
market gross rents and the elevated costs they faced, not an arbitrary figure.  
Renner asked about prior comments regarding ownership after the  
abatement term, and Postweiler clarified that the joint venture operated as an  
opportunistic seller. He said current market conditions did not favor a sale, but  
if interest rates fell and the building leased, they might exit. He could not  
commit to ownership duration, as that decision would depend on market  
dynamics.  
Councilmember Padova asked Postweiler to repeat earlier figures about  
Velocis. He stated that Velocis, headquartered in Dallas and founded in 2010,  
raised over $1.6 billion in equity and acquired more than $3.3 billion in real  
estate assets across over 220 investments, and that the Velocis-KBC  
partnership developed over $1 billion in industrial warehouse projects across  
15 developments totaling more than 8.5 million square feet. Padova then  
questioned the need-based rationale given the possibility of selling the  
warehouse before the abatement ended, asking whether the need stemmed  
from a requirement to recoup investment quickly to enable a sale. Postweiler  
replied that the need derived from market rental rates and competitive  
pressures, comparing what tenants would pay in their building versus  
alternatives in Columbus or New Albany. He introduced Beau Taggart to  
address market-related questions. Mr. Taggart said the tax abatement was  
essential to remain competitive in the marketplace, explaining that competing  
assets in New Albany and other areas offered 15-year, 100% abatements,  
which lowered their operating expenses and allowed them to offer more  
favorable lease rates. He said tenants evaluated multiple options, and without  
a competitive lease rate, the Gahanna building would sit vacant, forcing the  
owners to cover taxes, carrying costs, and utility expenses. He asserted that  
virtually no speculative building in the region operated without some form of  
tax abatement and that the project sought to meet current market demand.  
Mr. Postweiler supplemented that without the abatement they would need to  
deliver the building for just over $14 million in total project cost, but current  
costs exceeded $19 million. He said they lacked any other mechanism to  
absorb the $5 million gap, making the abatement necessary for the project to  
proceed. Taggart added that from an investor’s perspective, an abatement  
could complicate a future sale because buyers might worry about changes to  
gross or net rents when the abatement expired; ideally they would lease  
without an abatement, but competition made that unfeasible, so they pursued  
the abatement to satisfy present market demand.  
Joe Kimener said the proposed project represented the only competitive  
option in Gahanna for the company’s size requirements and that the city  
competed with other communities; he added that Gahanna could not win the  
project without the abatement. Vice President Weaver thanked Mr. Kimener  
and said his underlying concern centered on whether this project represented  
the best choice for Gahanna, not just in terms of use but in timing and given  
the site’s constraints, and asked why it was the right project for the city. Mr.  
Postweiler replied that the various Council meetings had demonstrated the  
community’s need for this product type, and he said that if the Council moved  
the Ordinance to the Regular Agenda in two weeks and approved it, they  
could take almost immediate action after the cooldown period by acquiring  
land and starting construction. He noted that the project held Planning  
Commission approval, a civil grading permit, and that they awaited only the  
abatement approval to proceed. He described existing site constraints and  
said those factors, along with the need for grant support from Jobs Ohio,  
underpinned the request. He contrasted the current $406 of annual benefit  
and zero jobs with the alternative of approving the abatement, which fell within  
average recent terms and percentages and included payroll guarantees and  
potential upside from job creation.  
Jordan Fromm of Value Recovery Group II LLC commented that the  
discussion about corporate structure mirrored his own experience with  
industrial development and that use of single-purpose entities with GP/LP  
tiers formed a common, sensible investment structure. He described his  
long-term ownership of the site since 2005, including the cleanup of the  
Bedford II landfill and the challenges in marketing the property, noting  
repeated interest from uncommitted prospects and that delays in approvals  
lengthened the sales cycle. He said they believed KBC represented a credible  
development partner.  
Bob Lockett of Alterra Real Estate recounted his involvement with the project  
dating back to approximately 2007 and recalled past challenges Gahanna  
faced competing with New Albany on abatements. He said the City of  
Gahanna had slowly achieved success in economic development and that, in  
evaluating partners, they performed their own research; he characterized the  
current development team as “AAA” and strongly recommended the Council  
consider the project carefully, warning that failure to approve it would have  
damaging consequences after years of effort.  
Director Gottke responded that no project proved perfect, acknowledged  
widespread concerns about performance and market changes, and said the  
city’s best approach involved securing the best deal while minimizing risk by  
evaluating partner indicators such as funding sources, Jobs Ohio support,  
and prior project success, and by relying on the city’s own land use, zoning,  
engineering, and abatement controls.  
Vice President Weaver said the exchange provided helpful level-setting and  
then called for any further questions or comments. Seeing none, he asked if it  
was the will of the Council to proceed with a vote on August 4, 2025.  
Councilmember Schnetzer asked whether the supporting documentation  
referenced during the discussion could be distributed by email to the Council,  
and City Attorney Tamilarasan agreed. Weaver requested, if available, any  
Jobs Ohio materials, and Mr. Postweiler said they remained under  
nondisclosure for the grant amount but could provide the draft grant  
agreement that Jobs Ohio issued to approved applicants. Weaver said that  
would be reasonable and asked that it be shared along with the other  
documents. He concluded that, with nothing further, they would proceed as  
planned on August 4, 2025.  
Recommendation: Second Reading/Adoption on Regular Agenda on 8/4/2025;  
Pending Amendment requested to remove Emergency Declaration.  
D.  
ITEMS FROM COUNCILMEMBERS:  
Councilmember Weaver:  
Resolution Honoring Kate Acklin, Franklin County Fair Queen  
Vice President Weaver noted that they were in the presence of royalty in  
Gahanna, explaining that the Franklin County Fair Queen, a resident of Ward  
4, had been announced the previous week. He said he would draft a  
resolution recognizing her, planned to work with the family as they gathered  
additional information about the process of becoming the Franklin County Fair  
Queen, and hoped to have a draft available for review. He requested, without  
objection, to do a ceremonial presentation at the August 4, 2025, Regular  
Meeting and said he would place the item on the Regular Agenda so  
members could view it in advance.  
E.  
ADJOURNMENT: