200 South Hamilton Road  
Gahanna, Ohio 43230  
City of Gahanna  
Meeting Minutes  
Committee of the Whole  
Trenton I. Weaver, Chair  
Merisa K. Bowers  
Jamille Jones  
Nancy R. McGregor  
Kaylee Padova  
Stephen A. Renner  
Michael Schnetzer  
Jeremy A. VanMeter, Clerk of Council  
Monday, April 14, 2025  
7:00 PM  
City Hall, Council Chambers  
A.  
CALL TO ORDER:  
Gahanna City Council met for Committee of the Whole on Monday, April 14,  
2025, in Council Chambers. Vice President of Council Trenton I. Weaver,  
Chair, called the meeting to order at 7:03 p.m. The agenda was published on  
April 11, 2025. Councilmember Nancy McGregor was absent. All other  
members were present for the meeting. There were no additions or  
corrections to the agenda.  
B.  
ITEMS FROM THE SENIOR DIRECTOR OF OPERATIONS:  
1. Gahanna Civic Center - 825 Tech Center Drive Update  
Gahanna Civic Center (825 Tech Center Drive) Construction Update  
4.14.2025  
Exterior, Interior, Upcoming Updates  
Senior Director of Operations Kevin Schultz provided the monthly update on  
the 825 Tech Center Drive renovation and expansion project. He was joined  
by Police Chief Spence to highlight progress specific to the Police  
Department’s facilities. Schultz noted that February had been relatively slow  
for construction, largely due to winter weather. However, in March of 2025, the  
pace picked up significantly, and progress resumed across multiple areas of  
the site. He reported that all utility work on the site, including water, sanitary,  
and storm systems, was complete and the team had begun site grading. All  
main rooftop heating, ventilation, and air conditioning (HVAC) units were  
installed during a Saturday lift, and the building was prepared for conditioning.  
The HVAC system was scheduled to be operational by mid-to-late May of  
2025, and the building was expected to be fully dried in by the end of April of  
2025.  
Interior progress included ongoing drywall finishing on the second and third  
floors. Schultz noted that the north-south wing of the third floor was drywalled,  
patched, and painted. Ceiling grid installation began in that wing, and the  
contractor planned to continue working from that area into the Police  
Department wing and down through the second and first floors. He provided  
updates on key infrastructure elements, including the installation of electrical  
switchgear, information technology (IT) cabinets, and shaft wall  
reconstruction. The interior shaft wall was removed and rebuilt to meet  
current code requirements, addressing a previous issue. Progress also  
continued in the Police Department’s holding facility. Schultz shared that he,  
Chief Spence, and several officers planned to conduct a walkthrough later in  
the week to finalize design and layout details, such as wall heights and the  
flow of space dedicated for mugshots and fingerprints. On the first floor,  
mechanical and electrical rough-ins were ongoing. Schultz confirmed that  
good progress continued and emphasized that the project remained on  
schedule.  
Senior Director Schultz stated that the furniture, fixtures, and equipment  
(FF&E) procurement process was underway, with responses due to the  
architect, MSA, by the end of the week. The Administration anticipated  
presenting the results at the second committee meeting in May of 2025. The  
City also issued a separate request for proposal (RFP) for moving and  
logistics, with proposals received the previous Friday, April, 11, 2025. To date,  
the project reached 61% completion and experienced 24 weather-related  
delay days. Schultz shared recent photos showing various areas of the  
building. These included the newly poured first-floor concrete in the future  
Mayor’s Court and City Council Chambers, painted walls in third-floor study  
rooms, rooftop HVAC units, an IT closet under construction, and newly  
installed electrical switchgear in the main electrical room. He noted that while  
some images might seem routine, they represented essential systems  
necessary for the building’s long-term functionality.  
March Financial Updates  
Senior Director Schultz continued the 825 Tech Center Drive project update  
with a review of the overall construction contract and financing structure. He  
presented a summary table showing the Guaranteed Maximum Price (GMP)  
components of the construction contract. The total project construction cost,  
comprising GMP 1 and GMP 2, was $59,627,855. As of the February pay  
application, 46% of the construction costs were invoiced, totaling  
approximately $27.5 million. The March invoice was not approved yet.  
Schultz reviewed the status of allowances and contingencies, reporting that  
$867,000 spent to date, representing approximately 26% of the total $4.7  
million allocated for those items. He then addressed a request from  
Councilmember Schnetzer to revisit original project assumptions. Schultz  
explained that the construction cost breakdown remained consistent with  
previous reports. Each GMP contract included construction expenses and  
costs related to allowances, contingencies, construction management fees,  
insurance, bonding, and commercial activity taxes (CAT). These components  
collectively comprised the $59.6 million total.  
Schultz moved on to a full project summary, outlining all costs beyond  
construction. The City purchased the 825 Tech Center Drive building for  
$8.75 million, including a $250,000 down payment noted on a subsequent  
slide. Design and pre-construction services were included, along with the  
$59.6 million construction figure. The FF&E (Furniture, Fixtures, and  
Equipment) budget stood at $1.6 million and was increased by $500,000  
using funds from a health and wellness refund. The additional funds  
supported staff wellness improvements such as height-adjustable desks  
across the facility. Additional project-related costs included third-party  
inspections (e.g., for steel and concrete), builder’s risk insurance, permitting  
and inspections, an easement agreement with American Electric Power  
(AEP), and the acquisition of two acres of land at the rear of the 825 property.  
Schultz concluded with a review of project financing. He explained that $3.3  
million in prior-year cash reserves, identified by the Finance Department in  
2021-2022, funded early planning efforts, including consultant MCP’s budget  
validation and the building’s down payment. Legal and consulting costs  
related to the property acquisition were also covered from this amount. He  
noted that the building purchase was ultimately rolled into the first bond  
issuance of $18.2 million, which also incorporated a 2012 bond refund.  
Although the refunded amount was not specified, Schultz clarified that the  
reduced total was not an error but an intentional accounting measure to avoid  
duplicating the building purchase in the financial summary. The second bond  
issuance occurred in June and totaled $33.5 million, covering the remaining  
project costs. The City also committed $10 million in cash to the project-$3  
million from the Capital Fund and $7 million from the General Fund, to support  
FF&E and contingency budgets. Schultz explained that any unused  
contingency funds would return to the cash allocation rather than the bond  
proceeds.  
Questions from Council  
Councilmember Schnetzer asked for clarification regarding the two  
bottom-line items on the financial summary slide, specifically, the $3 million  
and $7 million cash-funded contributions. He requested an explanation of why  
these amounts were funded with cash rather than through bonds. He noted  
his understanding that FF&E was excluded from bond funding due to its  
shorter life cycle, which did not align with the 28-year term of the bonds. He  
also asked for further clarification on the $7 million portion.  
Senior Director Schultz responded that, in consultation with Finance Director  
Joann Bury, the Administration determined that bringing $10 million in cash to  
the project was appropriate. Of that, $4.7 million was allocated for  
contingencies, $1.6 million for FF&E, and the remainder was rounded to an  
even $10 million to balance bond issuance and repayment considerations. He  
explained that FF&E expenses could not be financed through bonds because  
such items do not meet the minimum 28-year life span required for  
bond-funded capital expenditures. As a result, FF&E had to be funded with  
cash.  
Councilmember Schnetzer noted that contingency funds might ultimately go  
unspent. He emphasized that funding these amounts with cash instead of  
bonds avoided the risk of borrowing money that may not be needed and then  
paying interest on it for 28 years. Schultz confirmed that this was correct and  
added that the same principle also applied to the allowance line.  
Senior Center Covered Entryway  
Senior Director Schultz provided an update regarding ongoing discussions  
about the potential addition of a covered walkway at the entryway to the  
Senior Center portion of the 825 Tech Center Drive facility. He referenced the  
upper portion of a site drawing as the focal area for the discussion. Schultz  
reviewed the parking layout, noting that the facility included approximately 350  
to 360 total parking spaces. According to Americans with Disabilities Act  
(ADA) requirements, a facility of that size must have at least eight  
handicap-accessible spaces. The site currently includes 17 designated  
handicap parking spaces distributed throughout the lot. In addition, the City  
established a series of “limited mobility” parking spaces, shown in lighter blue  
on the drawing. These spaces are not legally enforceable but are intended as  
a courtesy to provide easier access for individuals with mobility limitations.  
Schultz explained that these spaces offer priority proximity to the building,  
although anyone may park there without penalty. A few of these limited  
mobility spaces were relocated from the front to the rear of the building,  
where access is actually closer. In total, 21 such spaces were provided, split  
roughly evenly between the front and back of the building.  
Schultz then focused on the proposed covered walkway at the Senior Center  
entrance. Staff engaged with the architect and construction manager, Elford,  
to obtain a rough order of magnitude (ROM) cost estimate. The estimated  
cost to design and construct the 23-foot-long covered walkway was between  
$300,000 and $350,000. Schultz illustrated the 23-foot distance by  
referencing the approximate space from Vice President Weaver’s seat to the  
front row of Council Chambers chairs. He explained that the team also  
evaluated the usage of the existing portico at the current Senior Center. Staff  
estimated that it was used for two to four drop-offs per week, though it often  
functioned more as a parking space than a dedicated drop-off area. Schultz  
stated that conversations with members of the Senior Center suggested that  
while the issue was important to a few individuals, it was not a widely shared  
concern among the membership as a whole.  
Schultz provided comparisons to similar facilities. Recently completed or  
soon-to-open senior centers in Westerville, Upper Arlington, and Hilliard do  
not feature covered walkways or porticos. In Upper Arlington, members must  
walk a considerable distance from a parking garage to the building. In  
Westerville, the uncovered distance to the entrance is approximately 30 to 35  
feet. He noted that cost, aesthetics, and functionality were key considerations  
in the evaluation. The architect expressed concern that a covered walkway  
added post-design could appear as an afterthought and detract from the  
building’s overall design. As an alternative, staff began exploring the idea of  
planting trees to form a natural canopy over the walkway rather than installing  
a structural one. Schultz concluded his remarks by inviting Police Chief  
Spence to speak on the public safety implications related to the proposed  
covered walkway.  
Police Chief Jeff Spence provided remarks regarding public safety concerns  
related to the proposed covered walkway at the Senior Center entry of the 825  
Tech Center Drive facility. He noted that although the building appeared large  
from the street, it became more scaled and compressed in appearance upon  
closer approach due to the curtain wall design and layout. He emphasized  
that the structure was multi-story, requiring accommodation for larger fire  
apparatus and emergency vehicles. Chief Spence explained that the curved  
roadway in front of the main entrance, where the covered walkway was  
proposed, was a very short and confined space. He expressed concern about  
the ability of a 60-foot ladder truck to navigate the space, calling it difficult if  
not impossible. He added that standing vehicles in that area would further  
complicate access for fire and Emergency Medical Services (EMS) vehicles,  
including squads, first responder engines, and others responding to detainee  
or walk-in medical emergencies. He pointed out that a key fire hydrant with  
direct connectivity to the building was located near the lower edge of the  
proposed area, as shown in the site rendering. This further limited feasible  
vehicle staging in front of the building.  
Chief Spence contrasted the proposed layout with the current Senior Center,  
where the existing overhang is located off the main travel way, allowing  
drop-offs to occur without obstructing circulation. In contrast, the front area of  
the new facility is part of a main travel way and serves as a primary  
circulation route around the building. He concluded by noting that, under  
existing conditions, the current Senior Center’s covered area was often used  
for parking rather than drop-off. This pattern further highlighted concerns that  
a new covered structure could become similarly misused and pose  
challenges for emergency access.  
Questions and Comments from Council  
Vice President Weaver thanked Senior Director Schultz and Chief Spence for  
their detailed follow-up on the proposed covered walkway at the Senior  
Center. He noted that he and several colleagues had previously reached out  
with questions and appreciated the consideration of potential alternatives to  
find the best possible solution.  
Councilmember Schnetzer raised concerns about the estimated cost of the  
walkway, noting that the back-of-the-envelope math suggested approximately  
$15,000 per linear foot. He asked what the primary cost drivers were. Schultz  
responded that the primary factor was that the structure was not part of the  
original construction plan. He explained that the cost of steel, which continued  
to rise, significantly impacted the estimate. Additionally, the design would  
require the installation of four footings, two bollards, and electric wiring in the  
roof structure. Schultz emphasized that electrical components in particular  
added substantial costs. He acknowledged his own surprise when the cost  
estimate came back at $300,000 to $350,000.  
Councilmember Padova sought clarification on the public safety concerns.  
She asked whether the issue was the physical presence of the canopy  
structure or the likelihood that cars would stop and block access. Chief  
Spence responded that it was a combination of factors. He noted that the  
drawing illustrated two parked vehicles measuring about 22 feet each. The  
total distance between the southernmost car and the apex of the roadway  
curve was less than 40 feet, making it extremely difficult-if not impossible-for  
large emergency vehicles to navigate the area. He clarified that the structure  
under consideration would not extend out far enough to function as a  
traditional overhang or portico, as site constraints would prevent that. The  
canopy would stop at the sidewalk, and the area would remain a main  
circulation route around the building. Spence emphasized that any vehicle  
stopping there, even briefly, would likely cause obstruction. Schultz added  
that in practice, a second vehicle would not likely stop where one was shown  
in the illustration. Instead, it would pull up behind the first car in the designated  
drop-off lane, which was constructed specifically for that purpose. He  
highlighted the curve of the roadway and the proximity to pedestrian areas as  
key design factors that guided the layout.  
Councilmember Padova asked about the nature and frequency of drop-offs at  
the current Senior Center. She inquired whether the facility regularly received  
vans or buses transporting groups of people, such as residents from assisted  
living facilities. Schultz responded that the two to four weekly drop-offs  
monitored by staff reflected individual drop-offs-not group trips. For larger trips  
or excursions, staff coordinated passenger loading away from high-traffic  
areas, though not necessarily under a covered structure. Padova clarified her  
question, asking whether the new facility would receive group drop-offs from  
assisted living communities, particularly those transporting individuals with  
mobility devices. Director of Parks and Recreation Stephania Ferrell  
confirmed that the city staff maintained partnerships with assisted living  
providers. She explained that these partners sometimes sponsored events  
and brought residents to attend. Ferrell stated that she did not view the lack of  
a covered walkway as a barrier. She emphasized that appropriate access to  
the facility was available, and that staff could provide accommodations during  
inclement weather as needed.  
Vice President Weaver referred to a prior walkthrough of the 825 Tech Center  
Drive facility with Senior Director Schultz, during which they discussed the  
feasibility of constructing a covered walkway at the rear of the building, near  
the dedicated Senior Center entrance. He asked Schultz to summarize those  
considerations on the record. Schultz explained that creating a similar  
covered structure at the rear of the building would require approximately  
double the distance compared to the proposed front walkway. He indicated on  
the site plan the location of the rear Senior Center member entrance and  
explained that the distance from the door to a potential drop-off point was  
significantly greater than the 23 feet required at the front. He added that the  
primary challenge with constructing a covered structure at the rear was  
related to traffic flow. The area immediately outside the rear entrance was  
part of a key north-south travel lane. Stopping or standing vehicles in that  
location would block most or all of the travel lane, creating significant  
disruptions to site circulation and posing safety concerns.  
Councilmember Padova followed up by asking whether any form of shelter  
would be provided at the rear entrance, especially since members would be  
required to use a badge or fob to access the door. Schultz confirmed that a  
small three- to four-foot overhang would be affixed to the building above the  
entrance. This structure, supported by the building itself, would provide  
minimal coverage for individuals as they accessed the entrance, protecting  
them from the elements while using their access credentials.  
Police Department  
Senior Director Schultz introduced the next portion of the presentation,  
focused on the Police Department’s training and operational facilities at the  
new 825 Tech Center Drive building. He noted that the layout emphasized  
efficiency, future expansion capacity, and the creation of a safe and secure  
facility. Schultz emphasized the intentional design separating staff and public  
spaces to enhance safety for employees, officers, and visitors alike. He then  
turned the presentation over to Police Chief Jeff Spence.  
Chief Spence began with an overview of the Police Department’s lower-level  
training center, located on the west side of the building. He described the first  
set of images, including an observation area with large windows looking into  
the range, the range itself with its backstop, and a storage area for equipment  
such as lane dividers. Adjacent to these areas were the simulator room and  
armory, as well as restrooms and secured storage space. The training center  
included multiple doors and features to maintain positive HVAC pressure,  
essential for safe environmental conditions. He also noted that this lower  
level, including its stair tower, served as the designated storm shelter for the  
entire facility-an important feature not available in current city buildings.  
Spence continued with the second section of the training center, highlighting  
the multi-functional training room, which will also serve as the City’s  
Emergency Operations Center (EOC) during major weather events or other  
emergencies. Additional images showed the fitness center and defensive  
tactics room. The defensive tactics room would allow for simulation-based  
training under stress, including scenarios like applying a tourniquet, where  
officers' fine motor skills may be tested. He noted that this type of high-stress,  
realistic training could help identify and resolve equipment or procedural  
issues in a controlled environment before they occur during actual calls for  
service.  
Spence then described the "monument stair," a central stairwell connecting  
all three floors of the Police Department. This stairwell would serve as a  
unifying space linking the field services and training areas on the lower and  
first floors to investigative services and administrative offices on the second  
and third floors. He noted that other police departments, such as those in  
Westerville, Hilliard, and Dublin, have done an excellent job preserving agency  
history, and the new monument stair would allow Gahanna to do the same.  
The stairwell would feature plaques honoring retirees and officers who  
served, including one who died in the line of duty and two who died while  
serving the City of Gahanna.  
To provide context for the improvements, Spence shared current images of  
the existing police facility across the street, focusing on the female locker  
room. The existing locker room included one stall, one shower, and one sink.  
Lockers were so closely spaced that two people could not open adjacent  
lockers at the same time. The lack of benches and storage space made the  
area cramped and inefficient. The space also doubled as gear storage,  
contributing to further congestion. In contrast, the new facility would separate  
gear storage into its own dedicated space near deployment areas, improving  
organization and operational efficiency. The locker rooms under construction  
would feature dedicated restroom facilities and a new HVAC system that  
circulated air not only into the room but directly into the lockers. This system  
would help dry wet equipment more effectively, reducing mold and odors, an  
important consideration given the challenging environmental conditions  
officers often face. Spence emphasized that these improvements would  
support both hygiene and overall staff well-being.  
Questions & Comments from Council  
Councilmember Schnetzer asked Chief Spence to comment on the  
importance of the structural hardening of the new police facility at 825 Tech  
Center Drive. He emphasized the need for the facility to remain operational in  
the event of a disaster, such as a tornado, and requested a summary of  
relevant design features for the public record.  
Chief Spence affirmed that the building will be constructed as a fully hardened  
public safety facility. He acknowledged that certain design improvements  
were made to the existing structure during both design and construction  
phases to enhance its durability and operational resilience. He confirmed that  
the facility will include a storm shelter and other components necessary to  
maintain functionality during emergencies. Spence recounted a prior incident  
from 2006 when a derecho storm caused two main doorways in the current  
police facility to blow out due to inadequate door strength. At the time, the  
facility was equipped with basic storefront doors that were neither hardened  
nor commercial grade, leaving the building unsecured. He further explained  
that the current facility contains additional vulnerabilities, including hollow core  
doors and unsecured window areas. In contrast, the new facility is being  
constructed with safety and security as top priorities. Design elements  
include standoff distance to control approach access, secure parking, and  
reinforced materials throughout. Spence noted that the Police Department  
would have two lobby areas: a hard lobby for initial public access and a soft  
lobby for secondary purposes such as taking police reports or conducting  
interviews. The new facility also includes a designated safe room for  
individuals in crisis who require immediate separation and protection. This  
room can be secured with minimal staff involvement and is designed to  
ensure occupant safety. He concluded by stating that the hardened design  
and emergency features would benefit the Police Department and other City  
staff working in the building.  
2. Capital Improvement Plan (CIP) Update  
Capital Improvement Plan (CIP) Presentation and Update 4.14.2025  
Senior Director of Operations Kevin Schultz provided an update on the  
Capital Improvement Plan (CIP) for the Committee of the Whole. He noted  
that the CIP Advisory Committee met in March of 2025, to begin reviewing the  
timeline and framework for the 2026 CIP update. Schultz reviewed the  
published CIP adoption timeline, noting that the draft CIP report would be  
introduced to Council on August 11, 2025, with final adoption targeted for  
September 2, 2025, following a second reading and public hearing. He  
reiterated that adoption of the CIP was not a formal approval of the capital  
budget itself. However, the 2026 CIP was expected to reflect approximately  
85-90% of the actual capital budget, with changes later presented as  
amendments during budget deliberations. In response to previous Council  
feedback, the Administration aimed to shift most capital-related presentations  
into August and September to reduce presentation time during October and  
November budget discussions.  
Schultz then discussed the continued evolution and maturation of the CIP  
document. He explained that while the document's intent remained  
consistent, the city administration updated project phases and terminology to  
reflect clearer planning expectations and eliminate confusion. In the past,  
project phases were labeled numerically by year groupings, Phase 1 (Years  
1-5), Phase 2 (Years 6-10), and so forth; this often led to misunderstandings  
about when projects were expected to begin. Instead, city administration  
proposed new terminology for project phases, aimed at better reflecting a  
project's status rather than a specific year:  
1. Actionable - Projects currently in design and scheduled for  
construction. These projects were financed and were progressing,  
such as 825 Tech Center Drive.  
2. Assessment - Projects undergoing feasibility analysis, including  
evaluation of cost, design, and funding needs. An example was the  
Clark State Road multi-use trail feasibility study with the Franklin  
County Engineer’s Office.  
3. Identified - Projects that were recognized but not yet evaluated for  
feasibility. These remained on the long-range planning list and could  
be promoted in the future.  
4. Visionary - Long-term conceptual projects, such as a hypothetical  
100-acre solar farm. These projects were aspirational and unlikely to  
proceed in the near term.  
Schultz emphasized that projects could move fluidly between categories as  
more information became available or as resources were allocated. He  
stressed that the key goal was not to tie project status to a rigid timeframe,  
but to maintain a clear categorization system that reflected feasibility,  
planning stage, and readiness for execution. He concluded by explaining that  
while some wording in the published document might still reflect the older  
“Phase 1-4” terminology, staff will update the language in consultation with the  
Advisory Committee and Council. The core intent of the plan, to identify,  
prioritize, and phase projects appropriately, would remain unchanged.  
Questions & Comments from Council  
Councilmember Jones asked whether the newly proposed terminology-such  
as "Actionable," "Assessment," and "Identified", would replace the “Start Year”  
currently shown in the Capital Improvement Plan (CIP) document. She asked  
if city administration would no longer include specific start years for projects.  
Senior Director Schultz confirmed that the shift in terminology would replace  
the use of a literal start year for most projects. For actionable projects, a start  
year such as 2025 would still be included, but for projects in the “Identified”  
phase, the column would instead show the label “Identified.” Schultz added  
that the heading for the “Start Year” column may also be updated to reflect  
this change.  
President Bowers followed up, asking whether allocating funding for feasibility  
assessments would automatically move a project from the “Identified”  
category into the “Actionable” category. Schultz clarified that it would not. He  
gave the example of the Clark State Road multi-use trail, noting that even with  
allocated funding for feasibility work, the project would only advance to the  
actionable category if Council explicitly authorized it. He emphasized that  
feasibility alone did not guarantee advancement to construction. President  
Bowers noted that the CIP Advisory Committee discussed the topic of  
feasibility extensively and found it to be a productive conversation. She  
highlighted that feasibility assessments should examine more than just cost  
and include considerations such as land availability and location constraints.  
Schultz agreed, citing the City’s service complex as an example. While the  
project remained a high priority, it remained in the assessment category due  
to the ongoing challenge of locating 10 to 12 acres of available land for the  
facility.  
Overview of Projects  
Senior Director Schultz continued the Committee of the Whole update by  
reviewing the nine largest capital projects currently identified within the City of  
Gahanna’s Capital Improvement Plan (CIP). He noted that while the following  
slides used an older nomenclature, referring to “short,” “mid,” and “long-term”  
project phases, he would update the terminology to reflect the revised  
“Actionable,” “Assessment,” “Identified,” and “Visionary” phases prior to  
distributing the final slide deck. Schultz explained that the nine projects  
represented a collective investment range of approximately $85 million to  
$105 million in today’s dollars. He clarified that while many of these projects  
were well-defined in terms of scale and scope, their prioritization and  
implementation varied. He also noted that some projects contained  
subcomponents with differing priority levels. For example, the Creekside  
Garage and Plaza project included a portion deemed imperative and  
therefore classified as a Priority 1 project, while other components were lower  
in priority. He further explained that the “Westside Utility Improvements”  
project, frequently referred to as the “Westside Sewer Project”, was renamed  
to better reflect its inclusion of water and storm sewer improvements in  
addition to sanitary sewer. The estimate of $12-16 million applied to Phase 1  
only and did not account for future phases that would increase the total  
investment further.  
Schultz then introduced the individual project slides, each of which included a  
project description, CIP phase (to be updated), priority level, detailed cost  
estimates for design, pre-construction, and construction, and potential  
funding sources. He informed the Council that the slide deck would be  
available for review and encouraged members to interrupt with questions as  
needed. The first detailed project discussed was the Big Walnut Trail, a  
multi-phase, long-term initiative more than ten years in the making. Schultz  
noted ongoing work to traverse I-270 via an Ohio Department of  
Transportation (ODOT) bridge project and stated that the City of Gahanna  
applied for LinkUS funding to help close the gap in the $4.35-$5.9 million  
project cost range. Estimated costs were broken out by easement  
acquisition, design and pre-construction, and construction phases.  
The next project highlighted was the Link to Literacy Trail. This trail would  
connect Hamilton Road to Creekside by way of Shull Park. Schultz explained  
that this project was currently classified as “Actionable” and “Essential,” due  
in part to the City’s leveraging of NatureWorks grant funding. He presented  
the full cost estimate of $2.1-$2.65 million, with breakdowns for land  
acquisition, design, and construction.  
President Bowers inquired about the grant funding associated with the Link to  
Literacy Trail project. Director Ferrell confirmed the City of Gahanna secured  
$500,000 in Clean Ohio Trail funding for the project. When asked whether the  
funding carried a timeline for use, Ferrell explained that while the funding was  
secured, the agreement was not initiated yet. Once a signed agreement was  
in place, the project timeline for construction would be determined.  
Senior Director Schultz then transitioned to an overview of the Creekside  
Garage and Plaza project. He noted that although the project was currently  
categorized under “Facilities,” it could also be considered a Parks project.  
Federal Emergency Management Agency (FEMA) mandated that the City of  
Gahanna mitigate flooding at the Creekside Garage; the City was working with  
Fishbeck to develop mitigation strategies. Schultz emphasized that FEMA’s  
requirement pertained only to flood mitigation, not to water seepage or  
waterproofing of the plaza itself, though those enhancements were also  
explored as a potential opportunity. The project was classified as “Actionable”  
due to its current status in the design phase and carried a Priority Level 1  
designation because of the FEMA flood mitigation requirement. Schultz noted,  
however, that only a portion of the project was truly imperative, while other  
components, such as plaza enhancements, could be considered  
discretionary. The scope of the project included garage and trail  
improvements, plaza reconstruction, streetscape enhancements, and ADA  
accessibility upgrades. The portion referred to as “garage and trail  
improvements” (shown in gray on the visual provided) would address  
FEMA-required mitigation and include ADA switchback ramps and stair  
access from the lower trail to the upper plaza. Schultz emphasized that this  
portion alone was estimated at $6.25-6.8 million.  
Senior Director Schultz further explained that the red and green portions on  
the slide represented the lower and upper plaza reconstructions, respectively.  
Councilmember Padova asked for clarification on what the green portion  
included. Schultz stated that it encompassed complete reconstruction of the  
plaza area, replacing street furniture, lighting, pavers, and railings, and  
installing new design elements such as decorative coverings and a fireplace  
feature. The upper plaza enhancements would also waterproof the garage  
ceiling beneath it. Padova confirmed with Schultz that the full $18.9-$22.3  
million project estimate reflected a complete reconstruction of the Creekside  
Plaza, not general maintenance, and matched the concept renderings that  
were shared with the public at the Mill Street Market. She requested that those  
renderings be shared with the Council again for reference, noting that some  
members may not have seen them.  
Senior Director Schultz also discussed anticipated funding sources, which  
included capital funds, TIF funds, and private investment. He explained that  
private investment was being sought in part to support utility relocation for the  
adjacent commercial buildings. In addition, the City recently applied for federal  
earmark funding to support the FEMA-required flood mitigation component.  
Mayor Jadwin added that this was the first year Ohio’s U.S. senators opened  
the opportunity for federal appropriations requests. The City of Gahanna  
submitted one application the previous Friday, April 11, 2025, and planned to  
submit two more in the upcoming week, including one through  
Congresswoman Beatty’s office.  
President Bowers asked whether the earmarked federal funds would apply to  
the FEMA-required mitigation. Schultz confirmed that they would and that the  
$6.25-6.8 million estimate for the garage and trail improvements was the  
portion for which earmark funding was requested. In response to a final  
question from Bowers, Schultz noted that there was no specific maximum  
award cap for this type of member-directed spending.  
West Johnstown Road Transportation Improvements  
Schultz presented the planned improvements for West Johnstown Road,  
including the segment from James Road to Goshen Lane. Although the map  
used during the presentation erroneously extended toward the interchange,  
the actual project limits ended at Goshen. The project, developed by Director  
Komlanc, included land acquisition, design and pre-construction, and  
construction phases. Schultz noted that this project would be coordinated  
with both the Westside Utility Improvements project and a Columbia Gas  
project scheduled for 2026 in the same corridor.  
Westside Utility Improvements  
Schultz outlined the scope and funding of the Westside Utility Improvements,  
emphasizing that the project addressed sanitary, stormwater, and water  
infrastructure simultaneously. The slide provided a detailed breakdown of  
funding allocations for each utility. Schultz noted that, since this work involved  
utility infrastructure, the project would be eligible for funding from specialized  
sewer, water, and stormwater capital funds, in addition to Tax Increment  
Financing (TIF) dollars. He added that completing all three utilities  
concurrently would provide long-term service improvements and avoid  
repetitive construction disruption.  
Service and Parks Garage Relocation  
Schultz discussed the proposed relocation of the service and parks garage.  
The current facility, situated on approximately 10 acres just north of  
Friendship Park, was inadequate. The City determined that relocating the  
facility would require 10 to 12 acres, but identifying suitable land within  
Gahanna remained a challenge. For this reason, the project remained in the  
“assessment” phase. Schultz explained that land acquisition costs in Central  
Ohio were driven up due to regional development pressures, including the  
regional Intel project, and estimated the cost of the acquisition at $1.5 to $2.5  
million for the needed acreage. Construction and pre-construction estimates  
were drawn from a past facility study by Pizzuti and updated using recent  
cost data from Elford, the City's partner on the 825 Tech Center Drive project.  
Aquatics Master Plan Implementation  
Schultz provided an overview of the Aquatics Master Plan, referencing a  
conceptual rendering of a potential new aquatic facility at Gahanna Swimming  
Pool (GSP). He clarified that the total project cost estimate of $21 to $26  
million only applied to reconstruction at GSP and did not include upgrades to  
the Hunter’s Ridge pool. Features in the conceptual design reflected  
community priorities, such as a relocated competition pool, zero-depth entry,  
slides, and a lazy river. The project remained in the "identified" or "midterm"  
phase of the Capital Improvement Plan. Schultz stated that the next step  
would be conducting a feasibility assessment to determine the viability of  
constructing the proposed facility.  
Councilmember Jones asked for clarification regarding the categorization of  
the Aquatics Master Plan project. She inquired whether, under the newly  
introduced CIP terminology, the project should be considered “visionary.”  
Senior Director Schultz responded that the project currently resided in the  
“identified” category, which is the third level of project readiness in the new  
framework.  
Stygler, Agler, US 62  
Senior Director Schultz then presented the final capital improvement project,  
the Stygler Road, Agler Road, and U.S. 62 intersection improvements. He  
acknowledged that while the community previously engaged in various  
planning efforts for the area, there remained no clear consensus or finalized  
direction. Schultz summarized that although several designs were presented  
in the past, the project ultimately lacked momentum and needed  
reinvigoration. He noted that Burgess & Niple were contracted through the  
City’s Comprehensive Transportation and Mobility Plan and were evaluating  
options for the intersection as part of their broader analysis. However, Schultz  
emphasized that the project lacked a defined scope or strategy at present  
and therefore remained in the “identified” category.  
Concluding Remarks  
Senior Director Schultz concluded by explaining the next steps for the  
administration. The City of Gahanna’s leadership team, including the Mayor,  
Director of Finance Joann Bury, and department directors, would begin  
internal discussions regarding potential funding strategies for the nine major  
projects. These discussions would precede and inform future meetings with  
the CIP Advisory Committee. Schultz suggested one possible strategy:  
implementing a multi-year capital budget approach. This approach would  
involve projecting and allocating revenue beyond a single fiscal year, enabling  
the City of Gahanna to begin financing longer-term projects by anticipating  
revenues from subsequent years. He clarified that this was only one example  
and that no decisions were made. He noted that these strategic  
conversations would continue during the June 2025 CIP Advisory Committee  
meeting, with the intent of advancing practical funding pathways for the larger  
capital priorities. He closed by noting that, while not one of the nine core  
projects discussed in detail, Academy Park was another large capital initiative  
and was already fully funded for 2025.  
Councilmember Padova thanked staff for the comprehensive information and  
noted that while some projects were familiar to her due to her participation on  
the Aquatics Steering Committee and her previous viewing of the Creekside  
concept at Mill Street Market, others might not be as familiar to her colleagues  
or members of the public. She asked whether the Council would receive  
additional presentations or updates on these projects prior to July of 2025.  
Senior Director Schultz responded that July would likely be the next  
opportunity to revisit these items unless a project needed advanced more  
quickly. He explained that, because the highlighted projects are large and will  
require long-term funding strategies, additional time is needed for planning.  
He also noted that while renderings can be helpful, they can also lead to  
confusion about the phase or status of a project. For that reason, staff have  
been careful to label renderings as “conceptual” and to refrain from showing  
them publicly until the appropriate stage of planning and funding.  
Councilmember Schnetzer thanked Senior Director Schultz for the overview  
and suggested the administration consider treating the Westside Utility  
Improvements project differently from a funding perspective. He noted that  
water and sewer-related infrastructure can legally be funded through  
revenue-backed bonds, which are secured by water and sewer charges and  
may allow for an alternative financing path if cash funding is not feasible.  
Councilmember Jones thanked staff for the presentation and asked for  
clarification on how the city administration will transition from the nine  
highlighted projects to the next set of projects, especially as the new CIP  
format moves away from assigning specific “start years.” She asked how  
projects like the community center would now be tracked. Schultz explained  
that each of the nine current projects addresses a specific and often urgent  
need, such as aging infrastructure, FEMA-mandated improvements, or  
long-term gaps in park facilities. He noted that the community center project  
is a good example of a long-range initiative that remains important but  
currently falls into the “visionary” category due to the cost, complexity, and  
land requirements involved. He added that being categorized as “visionary”  
does not preclude a project from moving forward as funding strategies or  
community priorities evolve. Councilmember Jones followed up, confirming  
that the community center project, while previously listed with a dollar  
amount, was not currently categorized under the new framework. Schultz  
confirmed that it will be placed in the “visionary” category in the updated plan.  
C.  
ITEMS FROM THE DEPARTMENT OF ENGINEERING:  
Returning for further discussion (Wynne Ridge Bridge):  
A RESOLUTION DECLARING THE CITY OF GAHANNA'S INTENT TO  
PARTICIPATE FINANCIALLY IN THE WYNNE RIDGE COURT BRIDGE  
REPLACEMENT PROJECT (ODOT PROJECT NO. 116417) AND  
AUTHORIZING THE MAYOR TO ENTER INTO A PARTICIPATORY  
AGREEMENT WITH THE OHIO DEPARTMENT OF TRANSPORTATION  
City Attorney Tamilarasan provided an update regarding the Wynne Ridge  
Bridge project, which is being completed in conjunction with the Ohio  
Department of Transportation (ODOT). She explained that ODOT originally  
submitted a sample resolution for the City's consideration, which appeared on  
the original agenda for first reading. However, Attorney Tamilarasan  
requested that the item return to Committee due to procedural concerns  
regarding the form of the legislation and potential conflicts with an ordinance  
previously passed in October of 2025. Attorney Tamilarasan noted that the  
resolution format was inconsistent with the type of authority being granted and  
that additional clarity was needed regarding what the City was authorizing  
ODOT to proceed with. She shared that she met earlier that day with  
ODOT’s Assistant Chief Counsel to clarify the required documentation. As a  
result of that meeting, a revised ordinance was created and uploaded that  
afternoon. The new ordinance replaces the resolution and amends the prior  
ordinance to reflect updated project estimates and contractual requirements.  
Two distinct documents were attached to the ordinance: a new Local Public  
Agency (LPA) contract and an amendment to the original LPA agreement.  
Both documents serve separate functions in enabling the City of Gahanna to  
move forward with the project. Because the ordinance authorizes a  
construction project, it would take effect upon signature. However, Attorney  
Tamilarasan advised that a waiver of second reading would be necessary in  
order to meet ODOT’s April 25, 2025 deadline.  
President Bowers thanked the City Attorney for her additional review and  
efforts.  
Vice President Weaver confirmed that both the resolution and ordinance  
would appear on the agenda for the upcoming meeting. Attorney Tamilarasan  
clarified that her recommendation was for the resolution to be tabled  
indefinitely, followed by a vote on the ordinance waiver, and then a vote on the  
ordinance itself. Vice President Weaver confirmed the process with Clerk  
VanMeter and thanked both Senior Director Schultz and Attorney Tamilarasan  
for their work on the matter.  
Recommendation: Postpone Indefinitely on Regular Agenda on 4/21/2025.  
AN ORDINANCE TO AMEND ORDINANCE 0058-2024 AND TO  
AUTHORIZE THE MAYOR TO PROVIDE CONSENT AND ENTER  
PARTICIPATORY  
AMENDMENTS  
AGREEMENTS  
WITH THE  
AND  
OHIO  
ANY  
DEPARTMENT  
NECESSARY  
OF  
TRANSPORTATION FOR BRIDGE REPLACEMENT ON WYNNE  
RIDGE COURT; AND WAIVING SECOND READING  
Recommendation: Introduction/First Reading on Regular Agenda with Waiver  
and Adoption on 4/21/2025.  
Request for Council Action (Fishbeck Engineering Services Proposal):  
AN ORDINANCE AUTHORIZING THE MAYOR TO ENTER INTO AN  
AGREEMENT WITH FISHBECK FOR UTILITY ENGINEERING  
SERVICES; AND DECLARING AN EMERGENCY  
Senior Director of Operations Kevin Schultz reported that on February 26,  
2024, the city issued a Request for Qualifications (RFQ) for engineering  
services. He explained that the RFQ served as a general solicitation covering  
various disciplines within the Engineering Department. Schultz stated that the  
city entered into a staff-type contract with Fishbeck for utility engineering  
services in 2024. This contract remains in effect until May 2, 2025. The  
purpose of the contract was to provide services previously handled by the  
city’s former Senior Utility Engineer. He noted that the position remained  
vacant since the departure of the previous engineer, despite continuous job  
postings and active efforts to recruit a replacement. He emphasized the  
critical importance of utility engineering to city operations. Schultz  
recommended entering into a new agreement with Fishbeck to continue  
providing utility engineering services. He clarified that the RFQ process from  
2024 remained valid and competitive, covering a two- to three-year period and  
still serving as a basis for contractor selection. He requested an ordinance  
authorizing the Mayor to enter into the agreement with Fishbeck. Given the  
upcoming expiration of the existing contract, Schultz also requested that the  
Council pass the legislation as an emergency measure.  
President Bowers asked for clarification on whether the Fishbeck utility  
engineering contract was related to the water engineering position the City  
previously experienced difficulty filling. Senior Director Schultz explained that  
the former Water Resources Engineer position was reclassified as the Senior  
Utility Engineer position several years ago, and confirmed it was the same  
role. He stated the position was vacant since approximately May of 2024, the  
previous year. The previous employee served as a project manager, but  
transferred to the Parks and Recreation Department in a lateral move during  
that time. President Bowers inquired whether a staffing realignment might  
help address the vacancy. Senior Director Schultz stated that hiring  
engineers was currently very difficult, and that hiring a utility engineer was  
even more challenging. Mayor Jadwin added that it was akin to "a needle in a  
haystack." Senior Director Schultz noted the city posted for multiple positions,  
including Senior Utility Engineer, Utility Engineer, and Utility Project  
Administrator, but applicants were scarce.  
President Bowers asked whether any of the responsibilities being proposed  
for Fishbeck could be handled internally by a different position. Senior Director  
Schultz explained that the tasks involved were highly specialized and required  
true utility engineering services, which no current staff member was qualified  
to perform. Bowers asked if other communities were experiencing similar  
challenges. Schultz confirmed that the position was posted in several  
neighboring municipalities, all facing similar difficulties. President Bowers  
acknowledged the challenge and expressed concern about the cost of the  
Fishbeck contract, noting that it appeared to be significantly more than the  
salary of a staff engineer. Schultz agreed, stating the position required a  
professional engineer (PE) credential. Bowers asked whether the position  
was in the correct classification and pay grade. Schultz responded that the  
position was upgraded to Senior Utility Engineer to ensure appropriate  
classification, though the current pay may not be competitive enough to  
attract qualified applicants. Mayor Jadwin added that paying more for the role  
than for the current City Engineer or Senior Transportation and Mobility  
Engineer would have broader compensation implications, and that the current  
contract approach was an effective way to meet the city's needs in the  
interim. Bowers asked whether the contract with Fishbeck could be canceled  
if the city hired someone for the position. Schultz confirmed that upon hiring,  
the Fishbeck contract would be phased out responsibly, and there was no  
commitment to the full expenditure.  
Vice President Weaver noted the contract was structured as “not to exceed”  
and that billing would occur only for actual work performed. Schultz confirmed  
that Fishbeck provided on-site services several days per week, and that the  
city received monthly invoices. Vice President Weaver emphasized the  
importance of ensuring the city had the staff it needed and welcomed a  
broader conversation about remaining competitive with other communities in  
order to attract and retain engineering talent.  
Councilmember Renner urged further research into the overall shortage of  
engineers, calling it a significant problem. Vice President Weaver  
acknowledged the challenge and agreed that all municipalities were  
competing for the same limited pool of qualified candidates.  
Recommendation: Introduction/First Reading on Regular Agenda on 4/21/2025;  
Second Reading/Adoption with Emergency on Consent Agenda on 5/5/2025.  
D.  
ITEMS FROM COUNCILMEMBERS:  
Councilmember Padova:  
1. Joint Resolution for Herb Week  
A JOINT PROCLAMATION AND RESOLUTION RECOGNIZING MAY  
3-10, 2025 AS HERB WEEK IN THE CITY OF GAHANNA  
Councilmember Padova introduced a joint proclamation and resolution  
created in collaboration with Mayor Jadwin to recognize Herb Week. She  
noted that the Council received the document earlier that day. The  
proclamation honored the city’s historical designation as the Herb Capital and  
recognized Jane “Bunnie” Geroux’s contributions in achieving that distinction.  
Padova announced that the proclamation would be presented to Director  
Kappes during the Herb Day celebration on May 3, 2025, at Creekside. The  
presentation was scheduled to take place on the backstage area just before  
the start of the celebration at 10:00 a.m., and she encouraged  
Councilmembers to arrive by 9:30 a.m. to participate. Mayor Jadwin asked if  
the version circulated to the Council was the same one she sent to  
Councilmember Padova earlier that day. Padova confirmed that it was.  
Recommendation: Introduction/Adoption on Consent Agenda on 4/21/2025.  
2. Joint Certificates of Recognition: GLHS Paperclip Project and GRIN  
Councilmember Padova informed the Council about the Paperclip Project  
currently taking place at Gahanna Lincoln High School. She noted that many  
Councilmembers had likely heard about the project or received emails from  
participating students. The project began in 2014 with the goal of collecting six  
million paperclips to create a monument honoring the victims of the  
Holocaust. Padova announced that students involved in the project would  
attend the next Council meeting. Students would speak about their work.  
Padova acknowledged scheduling was still being finalized due to end-of-year  
activities, including athletics. She shared that the Council Office prepared a  
certificate of recognition to present to the students in honor of their efforts.  
Vice President Weaver thanked Padova for the update and confirmed that no  
legislative action was required.  
Councilmember Padova continued by announcing that Gahanna Residents in  
Need (GRIN) would hold a ribbon-cutting ceremony for its new food lockers  
on Monday, April 21, 2025, at 5:30 p.m. She noted that the lockers were made  
possible in part by the City of Gahanna’s Community Grant funding. The  
Council Office would also prepare a certificate of recognition for GRIN, and  
she invited any Councilmembers who planned to attend the event to notify  
Clerk VanMeter or herself so their signatures could be included. For those  
unable to attend the event but who still wished to sign the certificate, Padova  
encouraged them to stop by Council Office prior to the event.  
E.  
ITEMS FROM COUNCIL OFFICE:  
Ohio Division of Liquor Control Notice to Legislative Authority Permit  
TRFO 4233752 FROM JAMES SNYDER DBA ANTOLINOS PIZZA TO  
JAMES SNYDER RESTAURANT GROUP LLC DBA ANTOLINOS  
PIZZA 1050 BEECHER CROSSING N STE G, GAHANNA, OH  
Clerk VanMeter informed the Council that the item under consideration was a  
transfer of ownership for Antolino’s Pizza. He reported that he contacted the  
Division of Police, which had no objections to the transfer. He stated that,  
unless the Council had any objections, he would proceed with notifying the  
state that a hearing was not requested. Vice President Weaver asked if there  
were any questions or comments from Council. Hearing none, he directed the  
Clerk to proceed accordingly.  
Note: Clerk returned notice to Division of Liquor Control indicating no hearing  
was requested.  
F.  
ADJOURNMENT:  
With no further business before the Committee of the Whole, the Chair  
adjourned the meeting at 8:57 p.m.